Over/Under Billings for Sage 100 Contractor

The two numbers that go on the balance sheet every month: billings in excess of costs and estimated earnings, and the reverse. Each job lands in one column or the other, as of the date you choose, and the figures equal the WIP report run with the same options.

It runs in your browser against your live Sage 100 Contractor data, through the Twinn service on your own network, and exports to Excel, PDF or CSV.

Over/Under Billings running in Twinn Reports
Over/Under Billings in Twinn Reports. Shown on a demo company; every name and number is made up.

Who uses it

  • Controllers posting the month-end WIP entry
  • CPAs reviewing percentage-of-completion
  • Owners watching cash against progress

The questions it answers

  • Which jobs are underbilled right now?
  • What is the total over/under billing for the balance sheet?
  • Which jobs moved from under to overbilled since last month?

Ask Twinn · Early access

“Which jobs are underbilled as of today, largest first?”

Ask Twinn, the assistant inside Twinn, runs this same report to answer questions in plain English. It tells you which report it ran, with which criteria, as of when, so the answer always matches the report.

How Ask Twinn works

What’s in the report

Every column, and what it means.

Job
Job number.
Job Name
Job name.
Status
Job status.
Contract
Original contract amount on the job.
Approved COs
Approved prime change orders approved by the as-of date (0 when the contract already includes them).
Revised Contract
Contract including approved change orders.
Estimated Cost
Total estimated cost of the job.
Est. Gross Profit
Gross profit expected at completion.
Est. GP %
Expected gross margin.
Cost to Date
Job cost posted up to the as-of date.
Complete %
Percent complete by cost.
Earned Revenue
Revenue earned by the work done so far.
Billed to Date
Amount billed up to the as-of date, retention included, sales tax excluded.
Over Billings
Billings in excess of costs and estimated earnings (a liability).
Under Billings
Costs and estimated earnings in excess of billings (an asset).
Gross Profit to Date
Profit earned so far.
Cost to Complete
Estimated cost still to be spent; negative when costs have passed the estimate.
Remaining to Bill
Contract not yet billed (backlog).

Criteria you can set

Pick these before you run it. Twinn remembers your last run.

  • As of
  • Jobs
  • Job
  • Job type
  • Supervisor
  • Budget and contract already include change orders
  • Permit costs to exceed estimate (Complete % over 100)
  • Skip $0 jobs

How it’s calculated

The same notes Twinn shows beside the report, so anyone reading it knows what the numbers include.

  • Percent complete is cost to cost: Cost to Date / Estimated Cost, capped at 100% unless you allow costs to exceed the estimate. Earned Revenue = Revised Contract x Complete %.
  • Over Billings (billings in excess of costs and estimated earnings) and Under Billings (costs and estimated earnings in excess of billings) are in separate columns; a job has one or the other.
  • Approved change orders approved on or before the as-of date add their approved amount to the contract and their budget to the estimated cost. Tick 'Budget and contract already include change orders' if your company posts approved COs into them.
  • Budgets and contract amounts are today's values: Sage keeps no history of them. Only costs, billings and change orders are cut off at the as-of date.
  • Leave 'As of' blank for everything posted. With the same as-of date and options, the figures equal Job Performance (WIP).